SEMI International Standards
Standards Locale: North America |
Committee: EHS |
Place of Meeting: SEMI HQ, San Jose, CA |
Date of Meeting: 11/10/2016 |
Meeting End Date: 11/10/2016 |
|
Recording SEMI Standards Staff: Kevin Nguyen |
CER Posted to Web: 11/15/2016 |
Leadership Changes
None.
Committee Structure Changes
None.
Ballot Results
Document # | Document Title | Committee Action | A&R Forms for Approved Ballots |
4683J | Line Item Revision to SEMI S2-0715, Environmental, Health, and Safety Guideline for Semiconductor Manufacturing Equipment. Delayed Revisions Related to Chemical Exposure | | |
Line Item 1 – Delayed Revisions Related to Chemical Exposure Criteria | Passed with technical changes. Ratification Ballot will be issued in cycle 9-16. | |
Ratification Ballot Results
None.
Activities Approved by the GCS between meetings of TC Chapter meeting
None.
Authorized Activities
# | Type | SC/TF/WG | Details |
6099 | SNARF | S22 Revision Task Force | Line Item Revisions to SEMI S2, Environmental, Health, and Safety Guideline for Semiconductor Manufacturing Equipment, and SEMI S22, Safety Guideline for the Electrical Design of Semiconductor Manufacturing Equipment |
6098 | SNARF | NA EHS TC | Reapproval of SEMI S3, Safety Guideline for Process Liquid Heating Systems |
Authorized Ballots
# | When | SC/TF/WG | Details |
R4683J | Cycle 9-16 | S2 Chemical Exposure Task Force | Ratification Ballot, Line Item Revision to SEMI S2-0715, Environmental, Health, and Safety Guideline for Semiconductor Manufacturing Equipment. Delayed Revisions Related to Chemical Exposure |
6049 | Cycle 1 or 2-17 | S10 Revision Task Force | Line Item Revision to SEMI S10-0815E Safety Guideline for Risk Assessment and Risk Evaluation Process |
4975 | Cycle 1 or 2-17 | S6 Revision Task Force | Line Item Revision to SEMI S6, EHS Guideline for Exhaust Ventilation of Semiconductor Manufacturing Equipment |
6098 | Cycle 9-16 | NA EHS TC | Reapproval of SEMI S3, Safety Guideline for Process Liquid Heating System |
6099 | Cycle 1 or 2-17 | S22 Revision Task Force | Line Item Revisions to SEMI S2, Environmental, Health, and Safety Guideline for Semiconductor Manufacturing Equipment, and SEMI S22, Safety Guideline for the Electrical Design of Semiconductor Manufacturing Equipment |
5970A | Cycle 1 or 2-17 | Fire Protection Task Force | Line Item Revisions to SEMI S14, Safety Guidelines for Fire Risk Assessment and Mitigation for Semiconductor Manufacturing Equipment |
SNARF(s) Granted a One-Year Extension
None.
SNARF(s) Cancelled
None.
Standard(s) to receive Inactive Status
None.
Special Announcements of the Committee (Workshops, Programs, etc.)
None.
Next Meeting
April 6, 2017 9 AM - 6 PM PDT at SEMI HQ in Milpitas, CA in conjunction with NA Spring meetings. Check www.semi.org/en/standards for latest update.
Draft schedule for task forces and TC Chapter is provided below.
Spring2017_Draft Schedule.xls
Copyright ©2024 Semiconductor Equipment and Materials International (SEMI®). All rights reserved.