Date Prepared: 01/10/2018Revised (if Applicable):

Document Number: 6340
SNARF for: Revision to SEMI F53-0600 (Reapproved 0412), Test Method for Evaluating the Electromagnetic Susceptibility of Thermal Mass Flow Controllers, with title change to Test Method for Evaluating the Electromagnetic Susceptibility of Mass Flow Controllers

Originating Global Technical Committee: Gases
Originating TC Chapter: North America
Task Force (TF) in which work is to be carried out: Mass Flow Controller Task Force
Note: If a new task force is needed, also submit a task force organization form (TFOF)

___________________________________________________________________________
1. Rationale:
a. Describe the need or problem addressed by this activity.
(Indicate the customer, what benefits they will receive, and if possible, quantify the impact on the return on investment [ROI] if the Document is implemented.)
Document 6214 was a Reapproval ballot that failed Committee review. SNARF 6214 was abolished at the
Fall 2017 meetings and this new SNARF is to be issued to incorporate and address the negatives and
comments that were received in Cycle 06-17.



b. Estimate effect on industry.
4: Slight effect or effect not determinable
Sector or Company Information:

c. Estimate technical difficulty of the activity.
I: No Difficulty - Proven concepts and techniques exist or quick agreement is anticipated

___________________________________________________________________________
2. Scope:
a: Describe the technical areas to be covered or addressed by this Document development activity. For Subordinate Standards, list common concepts or criteria that the Subordinate Standard inherits from the Primary Standard, as well as differences from the Primary Standard:
Title Change:
Test Method for Evaluating the Electromagnetic Susceptibility of Mass Flow Controllers

Address the negatives as follows:
-Remove the word “thermal” in the title, purpose, and scope as this Document applies to all mass flow
controllers.
-Modify Referenced Standards and Documents
-Make the primary units SI.
-Clarified some terms in the Definitions section


b: Expected result of activity
Major revision to an existing Standard or Safety Guideline

For a new Subordinate Standard, identify the Primary Standard here:


Modification of an existing part of Standard(s) or Safety Guideline(s) including Appendices, Complementary Files, and Supplementary Materials

For Standards, identify the Standard Subtype below:
Test Method

Miscellaneous (describe below):

___________________________________________________________________________
3. Projected Timetable for Completion:

a: General Milestones
a. Activity Start: 11/08/2017b. 1st Draft by: 02/09/2018
c. (Optional) Informational Ballot by: d. Letter Ballot by: 02/21/2018
e. TC Chapter Approval By:04/10/2018

_____________________________________________________________________________
4. Liaisons with other Global Technical Committees/TC Chapters/Subcommittees/TFs:
a.
List SEMI global technical committees, TC Chapters, subcommittees, or task forces in your or other Regions/Locales that should be kept informed regarding the progress of this activity. (Refer to SEMI Standards organization charts and global technical committee charters and scopes as needed.)


b. List any planned Type I Liaisons with external nonprofit organizations (e.g., SDO) that should receive Draft Documents from Standards staff for feedback during this activity and be notified when the Letter Ballot is issued (refer to Procedure Manual § 7):


c. Intercommittee Ballots:
will not be issued

Identify the recipient global technical committee(s):

___________________________________________________________________________
5. Safety Considerations:
The resulting document is expected:
NOT to be a Safety Guideline

NOTE FOR "to be a Safety Guideline": When all safety-related information is removed from the Document, the Document is NOT technically sound and complete - Refer to Section 15.1 of the Regulations for special procedures to be followed.

NOTE FOR "NOT to be a Safety Guideline": When all safety-related information is removed from the Document, the Document is still technically sound and complete.

___________________________________________________________________________
6. Intellectual Property Considerations:
a. For a new Standard or Safety Guideline and for any part to be modified or added in a Revision of published Standards and Safety Guidelines:


If "patented technology is intended to be included in the proposed Standard(s) or Safety Guideline(s) " is selected above, then also check one:


b. For Revision, Reapproval, Reinstatement, or Withdrawal of existing Standard(s) and Safety Guideline(s):
there is no known material patented technology necessary to use or implement the Standard(s) and Safety Guideline(s)

c. The body of the Document and any Appendices, Complementary Files, Related Information sections, or Various Materials that may or may not be a part of the Document by reference:



NOTE FORthe use of patented technology or the incorporation of Copyrighted Item(s) is NOT required’: If in the course of developing the Document, it is determined that the use of patented technology or Copyrighted Item(s) is necessary for the Document, the provisions of Regulations § 16 must be followed.

NOTE FORwill incorporate Copyrighted Item’: A copyright release letter must be obtained from the copyright owner prior to publication.

___________________________________________________________________________
7. Comments, Special Circumstances:
Passed A&R Cycle 8-2019

__________________________________________________________________________
8. TC Member Review:
took place between (put dates below) before approval by the GCS, or

Member Review Start Date; 01/10/2018
Member Review End Date: 01/23/2018

NOTE FOR ‘TC Member Review’ is required by the Regulations for a period of at least two weeks
before approval of a new, or a major revision of an existing, Standard or Safety Guideline. (Refer to Regulations ¶ 8.2.1)
__________________________________________________________________________

9. SNARF Approval Dates:
TC Chapter or GCS02/05/2018
Recorded in TC Minutes04/10/2018

__________________________________________________________________________

10. SNARF Extension Dates:
TC Chapter Extension Granted on
Extension Expires on