SEMI International Standards
Standards New Activity Report Form (SNARF)
Date Prepared: 06/16/2022Revised (if Applicable):

Document Number: 6974
SNARF for: New Standard: Specification for Rich Interactive Test Database Event Message Content

Originating Global Technical Committee: Automated Test Equipment
Originating TC Chapter: North America
Task Force (TF) in which work is to be carried out: Rich Interactive Test Database (RITdb)
Note: If a new task force is needed, also submit a task force organization form (TFOF)

___________________________________________________________________________
1. Rationale:
a. Describe the need or problem addressed by this activity.
(Indicate the customer, what benefits they will receive, and if possible, quantify the impact on the return on investment [ROI] if the Document is implemented.)
While SEMI E183 defines the structure for event messages it does not define the content nor meaning of event messages.

For the effective use of SEMI E183 event messages there must be a standard controlling these messages. This standard will be for the core operational messages (e.g. test, material, environment, etc.) needed to communicate changes within a semiconductor test environment using SEMI E183.



b. Estimate effect on industry.
2: Major effect on an industry sector - identify the relevant sector
Sector or Company Information: Test equipment companies

c. Estimate technical difficulty of the activity.
II: Some Difficulty - Disagreements on known requirements exist but developing consensus is possible

___________________________________________________________________________
2. Scope:
a: Describe the technical areas to be covered or addressed by this Document development activity. For Subordinate Standards, list common concepts or criteria that the Subordinate Standard inherits from the Primary Standard, as well as differences from the Primary Standard:
Event messages may be passed between equipment, applications and data sources within and between semiconductor test environments. Messages may contain test data, events, commands, history, recipes and other data items as required. This standard will cover content and meaning for common event messages.

Messages could include material status, run status, equip status, errors, action, etc. but are not limited to these.


b: Expected result of activity
New Standard or Safety Guideline (including replacement of an existing Standard or Safety Guideline)

For a new Subordinate Standard, identify the Primary Standard here:




For Standards, identify the Standard Subtype below:
Specification

Miscellaneous (describe below):

___________________________________________________________________________
3. Projected Timetable for Completion:

a: General Milestones
a. Activity Start: 06/16/2022b. 1st Draft by: 08/01/2022
c. (Optional) Informational Ballot by: d. Letter Ballot by: 10/01/2022
e. TC Chapter Approval By:02/01/2023

_____________________________________________________________________________
4. Liaisons with other Global Technical Committees/TC Chapters/Subcommittees/TFs:
a.
List SEMI global technical committees, TC Chapters, subcommittees, or task forces in your or other Regions/Locales that should be kept informed regarding the progress of this activity. (Refer to SEMI Standards organization charts and global technical committee charters and scopes as needed.)


b. List any planned Type I Liaisons with external nonprofit organizations (e.g., SDO) that should receive Draft Documents from Standards staff for feedback during this activity and be notified when the Letter Ballot is issued (refer to Procedure Manual § 7):


c. Intercommittee Ballots:
will not be issued

Identify the recipient global technical committee(s):

___________________________________________________________________________
5. Safety Considerations:
The resulting document is expected:
NOT to be a Safety Guideline

NOTE FOR "to be a Safety Guideline": When all safety-related information is removed from the Document, the Document is NOT technically sound and complete - Refer to Section 15.1 of the Regulations for special procedures to be followed.

NOTE FOR "NOT to be a Safety Guideline": When all safety-related information is removed from the Document, the Document is still technically sound and complete.

___________________________________________________________________________
6. Intellectual Property Considerations:
Note: Both a: and b: below should be checked for Revision of existing Standard(s) and Safety Guideline(s).

a. For a new Standard or Safety Guideline and for any part to be modified or added in a Revision of published Standards and Safety Guidelines:
the use of patented technology is NOT required.

If "patented technology is intended to be included in the proposed Standard(s) or Safety Guideline(s) " is selected above, then also check one:


b. For Revision, Reapproval, Reinstatement, or Withdrawal of existing Standard(s) and Safety Guideline(s):
there is no known material patented technology necessary to use or implement the Standard(s) and Safety Guideline(s)

c. The body of the Document and any Appendices, Complementary Files, Related Information sections, or Various Materials that may or may not be a part of the Document by reference:
the incorporation of Copyrighted Item will NOT be required



NOTE FORthe use of patented technology or the incorporation of Copyrighted Item(s) is NOT required’: If in the course of developing the Document, it is determined that the use of patented technology or Copyrighted Item(s) is necessary for the Document, the provisions of Regulations § 16 must be followed.

NOTE FORwill incorporate Copyrighted Item’: A copyright release letter must be obtained from the copyright owner prior to publication.

___________________________________________________________________________
7. Comments, Special Circumstances:
None.

__________________________________________________________________________
8. TC Member Review:
took place between (put dates below) before approval by the GCS, or

Member Review Start Date; 7/7/2022
Member Review End Date: 7/21/2022

NOTE FOR ‘TC Member Review’ is required by the Regulations for a period of at least two weeks
before approval of a new, or a major revision of an existing, Standard or Safety Guideline. (Refer to Regulations ¶ 8.2.1)
__________________________________________________________________________

9. SNARF Approval Dates:
TC Chapter or GCS07/28/2022
Recorded in TC Minutes

__________________________________________________________________________

10. SNARF Extension Dates:
TC Chapter Extension Granted on
Extension Expires on